Project
Name:
REHABILITATION
OF ENTEBBE AIRPORT RUNWAY AND AIR SIDE FACILITIES
Duration
of Assignment: 18
staff months
|
Country:
Uganda
Location: Entebbe |
Client:
Colas, Pihl and Intertec (CPI) Joint venture
116, Nybrovej
2800 Lyngby, Denmark
Tel: +45 45 27 72 00
|
No.
of staff: Four
Professional staff provided:
Land surveyors, Auto CAD specialist. |
|
|
Start
Date: 1995 |
Completion
Date: 1996 |
|
Description
of Project:
Resurfacing of the airport runway and taxi ways,
reinstallation of runway and taxi way lead-in lights,
approach lights, cameras and markings. Construction of
a new fire house, sewer and drainage facilities. Construction
of a perimeter and access roads. Expansion and improvement
of the existing apron.
Actual
services provided: |
- Setting
out of runway and taxi way centre lines, edge lines,
cross falls, edge-lights and chambers
- Setting
out of apron lead-in lines, stop lines, hydrant pits,
lights and reinforced parking pads
- Setting
out of access roads, jetties, sewer lines and drainage
- Positioning
of approach lights and chambers
- As
built measurements of lights, chambers, access roads,
underground cables and runway navigational facilities
|
|